Overview
In TopTeam, you can revert a project to a baseline by creating a branch from baseline, and deleting the existing project.
This article explains how to revert a project to a baseline.
Prerequisite
You should be a Project Administrator to revert a project to a baseline.
Step 1. Create a branch from a project baseline
While creating a project branch, select a desired baseline from which you want to create a project. Also, ensure that you add all record types and issue types while creating it.
NOTE: The Baseline that you select to create a project branch must be a Complete Baseline.
Refer to the following process demonstration on creating a branch from a baseline:
The project from a baseline will be created and displayed in the repository.
Step 2. After branch has been created from a baseline, delete the existing project
Step 3. Confirm deletion of the project
Revised: January 18th, 2021